The challenge
The device was worth £250k and had to stay horizontal the whole way in. The doorway was tight, with up and down steps on the route.
None of that shows on a drawing. It showed up on the site survey.
Our approach
The survey found that the door and frame needed to be removed. With them out there was just enough room, and next to none to spare. For the steps we built lite deck staging with custom scaffold legs to bridge the up and down, keeping the device level.
On laboratory moves generally we check access, write the RAMS, protect the route and keep a chain of custody. Decontamination, calibration and commissioning stay with the client or the manufacturer.
The result
The scientific device was delivered and installed, with the door and frame dealt with as part of the job.