The challenge
Acoustic pods and booths arrive flat in long, heavy boxes. Each box is about 2.2 m long and weighs 60 kg, and a phone booth takes six of them. Offices don't want that happening while people are working, so the installs ran on Saturdays and out of hours.
The six-person Saturday job covered several floors.
Our approach
We matched the crew and the vehicle to each job. The largest visit was a Saturday with a six-person team, installing five meeting pods and a couple of single-person booths across several floors.
For ten phone booths we sent a truck with a 2.5t cantilever tail lift.
Inside the building, boxes moved on plasterboard trolleys.
Smaller visits followed: two meeting rooms in one, six booths in another. In February 2025 two of us dismantled a meeting room and rebuilt it in a different part of the same building, again on a Saturday.
The result
Every install was finished. Between March 2024 and February 2025 that meant the five-pod Saturday, two meeting rooms, ten phone booths, six booths and the final rebuild.