Our engineer decommissioning a rack.

Paris moves, final decommission and on-site shredding

In February and March 2023 we ran a two week phased project for an investment bank. Engineers cable traced and de-racked kit. We then ran two data centre relocations and a server relocation to Paris, with customs cleared and delivery direct to site, and our HSM shredder went on site for the final decommission.

Client type
An investment bank
Scope
Cable tracing and de-racking, data centre and server relocations to Paris, customs clearance, final decommission of 4 racks with on-site shredding
When
February to March 2023
Where
Paris, France
Results
£0.5m of kit insured on the data centre moves, a server relocation insured at £250k and delivered before midday, 4 racks decommissioned

The challenge

The client was moving its equipment to Paris in stages, and the old estate still had to be emptied and cleared at the end. That is three different jobs: move the kit out, get it across a border, and deal properly with whatever is left behind.

As we put it at the time: put it in, take it out and manage the whole end of life cycle.

Our approach

In order:

  • On 23 February a couple of our engineers were on site cable tracing and de-racking several devices for the staged migration to Paris.
  • On 24 February two of our team were in Paris on two data centre relocations. The kit was insured at £0.5m under our marine cargo policy, customs was cleared and the loads were delivered direct to site. The last van was on the Eurotunnel at Calais.
  • On 2 March we moved a server relocation to Paris before midday. It was insured at £250k, pre customs clearance was done in advance, and it was delivered direct to site in a Renault Trafic.
  • On 3 March our HSM Powerline HDS 150 shredder went out on site for the final decommission of 4 racks, with the equipment going on for recycling and WEEE certification.

Here is how we normally run the shredder on site:

  • Drives are audited, and make, model and serial are scanned into a certificate of destruction.
  • The HSM cuts to a 40 mm strip, at up to 210 drives per hour.
  • It runs from a 13 amp socket or from a 7 kW generator in the vehicle.
  • Equipment goes to a WEEE recycling partner for certification. Kit can also be stored, reused, recycled or donated.

The result

A two week phased project from cable trace to final decommission. Two data centre relocations to Paris insured at £0.5m, a server relocation insured at £250k and in Paris before midday, and 4 racks decommissioned with the shredder on site, then sent for recycling and WEEE certification.

Yes. The shredder travels in our vehicle and runs from a 13 amp socket or a 7 kW generator, so the decommission can follow the move at the same site.

Drives are audited and recorded before they go in. Tell us the drive count and we'll work out the time.

We handle pre customs clearance with our in-house customs agent, so loads can be delivered direct to site. Our own tools and handling kit travel on our ATA carnet. Send us the kit list and the route early, because the paperwork takes longer than the drive.

Equipment goes to a WEEE recycling partner for certification. Where the kit still has value, it can instead be stored, reused or donated. Tell us at the start which route you want, so the decommission is planned to match it.

Related case studies

See all case studies

Services used

Moving kit abroad and clearing the old site?

Tell us the route and the rack count, and we'll plan the border and the decommission together.

We reply to every enquiry. Your details are used only to answer it. Privacy notice

Thank you, your enquiry has been sent

We have your details. Someone from the team will read it and come back to you by phone or email.

CallGet a quote